The Alaska Railroad's board of directors has given final approval to finishing the Port MacKenzie Rail Extension, and the railroad's chief executive says the goal is to break ground next summer, the Alaska Beacon reported Nov. 20. CEO Bill O'Leary told the Beacon the start date depends on how fast the Federal Railroad Administration finalizes the grant and other required approvals, and that he expects to know more within about four to six weeks.

Nov. 21, 2026. Compiled from Alaska Railroad records and published reports.

The planned 32-mile line would connect the Mat-Su Borough's port on Knik Arm to the railroad's main line at Houston. In October the Federal Railroad Administration awarded the railroad $249 million toward the project, which the railroad puts at about $311 million in total, according to the railroad's Oct. 19 news release. The grant program requires a 20 percent local match, about $62 million, which the railroad says will come from in-kind contributions by the Mat-Su Borough and cash from the railroad and the Alaska Industrial Development and Export Authority.

The board packet for the railroad's Nov. 17 meeting shows the full $311.3 million in its proposed 2027 capital budget: $249.05 million in federal money and a $62.26 million match from the railroad, AIDEA and the borough. The same agenda listed three Port MacKenzie resolutions: ending the railroad's memorandum of understanding with Alaska Infrastructure Partners, a private group that had proposed to build and finance the line; completing the project with the federal grant; and asking the state to transfer land the railroad says it needs for the project.

AIDEA's share of the match, about $33 million according to the Beacon, is still pending. Its board recessed on Nov. 19 without voting and is set to resume Nov. 24. Gov.-elect Jonathan Kreiss-Tomkins has asked the board to hold major decisions until he takes office Dec. 7. O'Leary told the Beacon he does not expect the incoming governor to oppose the rail project. Our Nov. 20 story has more on the AIDEA meeting.

What we could not confirm

We have not seen the minutes or vote tally from the railroad board's Nov. 17 meeting, so the final approval rests on O'Leary's account to the Beacon. We have not confirmed the outcome of the two other Port MacKenzie resolutions. AIDEA's $33 million figure comes from the Beacon; railroad records list AIDEA as a match source without naming an amount.

Sources

Accessed Nov. 21, 2026.

  • Alaska Railroad, news release on the Federal Railroad Administration CRISI grant, Oct. 19, 2026 (PDF): alaskarailroad.com
  • Alaska Railroad Board of Directors, Nov. 17, 2026 meeting packet, including agenda and 2027 capital budget (State of Alaska Online Public Notices attachment): aws.state.ak.us; meeting notice: aws.state.ak.us
  • Alaska Beacon, "Port MacKenzie rail construction could come as soon as summer, Alaska Railroad CEO says," Nov. 20, 2026: alaskabeacon.com (republished by the Anchorage Daily News)

More Economic Development